Offshore Load Out Installation For Mepa Float Over Topside

 

Scope of Work

  1. To check condition of generator and hydraulic system after sailing from Kuching.
  2. To install remote control hose and electric cable from power pack to remote unit.
  3. To perform lifting of topside to required height. Lift up till 3.25m height.
  4. Lowering topside after barge and topside locate at exactly position. At height 2m during lowering, dump button activated to allow free fall of topside.
  5. Housekeeping to keep work site safe and tidy.